EV Charging

    Park Garage Group PLC — Rushden

    Design, grid connection, and installation of 2x 480kW DC ultra-rapid EV chargers at a new-build site in Rushden for Park Garage Group PLC.

    Park Garage Group PLC — Rushden client logo
    Park Garage Group PLC — Rushden — photo 1

    Location

    Land at John Clark Way, Rushden, NN10 0FW

    Sector

    Fuel Retail / Forecourt

    Duration

    12 weeks

    Services

    Grid Connection, EV Charging, Civil Works, Project Management

    THE CHALLENGE

    Park Garage Group PLC required 2x 480kW DC ultra-rapid EV chargers at a new-build site in Rushden, Northamptonshire. The greenfield location needed a full grid connection, civil groundworks, and charger installation — all delivered to a tight programme to align with the wider site development.

    OUR APPROACH

    Spiral Renewables delivered the full project from feasibility through to commissioning — including DNO grid connection application, civil engineering, electrical installation, and charger deployment.

    We managed all contractor coordination on site, ensuring the EV charging infrastructure was delivered in step with the broader development programme and to the highest safety and quality standards.

    THE OUTCOME

    The Rushden site was delivered on time and on budget, providing 2x 480kW DC ultra-rapid EV charging capability at a strategically important location in Northamptonshire. The hub is now operational and serving both commercial and consumer EV drivers.

    KEY DELIVERABLES

    Full DNO grid connection application and approval

    Civil groundworks including trenching, ducting, and surface reinstatement

    2x 480kW DC ultra-rapid charger installation and commissioning

    Canopy and lighting infrastructure

    Payment and back-office system integration

    Ongoing maintenance and support agreement

    Want similar results for your project?